Naturgy Solar Park in Albacete: 49.35 MW hybridized with wind energy
Naturgy Vento obtains authorization for a 49.35 MW solar park in El Bonillo (Albacete) that will be hybridized with the ...
12 Articles
Naturgy Vento obtains authorization for a 49.35 MW solar park in El Bonillo (Albacete) that will be hybridized with the ...
The 62.7 MW Taraguilla wind project in Cádiz is archived following the developer's withdrawal. Key insights for renewabl...
The Pasama wind farm (50.10 MW, Soria) is cancelled after losing its grid connection permits by exceeding the deadlines ...
The Cerro de Magaña wind project (50 MW, Soria) is cancelled after its grid connection permits expire due to a late EIA....
Statkraft withdraws the Lagunillas wind project (65.7 MW, Málaga) due to environmental unfeasibility. File PEol-958 is a...
Statkraft withdraws from the Arrebol wind farm (58.1 MW, Cádiz) following unfavorable environmental assessment. The file...
The unfavorable EIA and expiration of grid connection permits have blocked the 86.8 MW Benavieja wind farm in Cantabria....
Arena Green Power withdraws from its 50 MW wind farm in Asturias for failing to obtain the EIA before the RDL 23/2020 de...
Enel Green Power withdraws the hybrid project «El Tambor-HB6» (132 MW) in Teruel due to Environmental Impact Assessment ...
Enel Green Power obtains prior administrative authorization for 107 MW hybrid in Teruel. Discover what it means for rene...
Greenalia obtains the public utility declaration for the 52 MW Orzar wind farm in Carballo, Tordoia and Val do Dubra. Af...
The Bustatur wind farm of 41.6 MW obtains a declaration of public utility. Landowners in Cantabria and Burgos face expro...