Energy

400 kV Power Line Almazán-Coscurita: EIA Approved and Conditions for Red Eléctrica

E
Equipo Editorial CambiosLegales
Oct 28, 2026 7 min 1 views

Key data

RegulationResolution of October 7, 2026, from the Directorate General for Quality and Environmental Assessment
PublicationOctober 28, 2026
Entry into forceOctober 28, 2026
PromoterRed Eléctrica de España
Affected partiesRed Eléctrica de España and administrations of Castilla y León affected by the infrastructure
CategoryEnergy / Environmental Assessment
Line length597 meters
Voltage400 kV, single circuit
Number of supports3 steel lattice supports
Estimated execution period2 months
SectionAlmazán substation — new Coscurita substation (Soria)
Impact analysis reserved for subscribers
The detailed impact analysis of this regulation is available with the PRO and Business plans. Access the full content and receive personalized alerts.
From €9.99/month · Cancel anytime

Red Eléctrica de España has received environmental approval to build the 400 kV overhead power line between Almazán and the future Coscurita substation in the province of Soria. The Resolution of October 7, 2026 from the Directorate General for Quality and Environmental Assessment, published in the BOE on October 28, 2026, issues the environmental impact assessment (EIA) with a favorable conditional nature.

The project responds to the State's binding electrical planning and the high wind potential of the area, making this infrastructure a key node for renewable energy evacuation in Castilla y León. The EIA is not a minor procedure: without it, the work cannot legally begin, and its content sets the rules for the entire construction and operation phase.

597 m
Total length of the overhead power line
400 kV
Line voltage, single circuit
3
Steel lattice supports planned
2 months
Estimated execution period for the work

What does this regulation establish?

The approved EIA authorizes the project with impacts rated as compatible in the most sensitive aspects—atmosphere, noise and electromagnetic fields—thanks to the distance from inhabited areas: all are located more than 1 km from the line and no dwellings are detected in the 100-meter buffer.

However, the resolution imposes corrective conditions that Red Eléctrica must comply with mandatorily. These conditions are structured around four major blocks:

Conditions blockMain content
Noise and emissionsMeasures during the construction phase to minimize acoustic impact and atmospheric emissions
Waste managementProtocol for waste management and removal generated during work execution
Cultural heritage protectionSpecific conditions to protect the cultural heritage of the surrounding area during work
Sectoral organism conditionsRequirements derived from reports by the Duero River Basin Authority and the Junta de Castilla y León

The technical justification of the project is based on two pillars: the State's binding electrical planning and the high wind potential of the Soria area, which requires new evacuation capacity to the transport network.

Economic and operational impact

For Red Eléctrica de España, EIA approval unlocks the construction phase of the Coscurita substation and its connection to the 400 kV network. This is a short-distance infrastructure—597 meters—but of high strategic relevance for renewable integration in the area.

From an operational perspective, the most relevant aspects are:

  • Estimated execution period: 2 months. A very tight schedule that requires precise planning of corrective measures from the first day of work.
  • Conditions from the Duero River Basin Authority: Involve restrictions or specific requirements on water management and public hydraulic domain in the project's area of influence.
  • Conditions from the Junta de Castilla y León: Add an additional layer of regional supervision, with possible requirements on biodiversity, soil or cultural heritage.
  • Electromagnetic fields: Rated as compatible since no dwellings exist in the 100-meter buffer, eliminating the risk of neighbor complaints on this matter.

Non-compliance with any of the EIA conditions may result in work stoppage or administrative sanctions, so regulatory compliance has a direct economic impact on the project schedule.

Who does it affect?

  • Red Eléctrica de España: Project promoter and main party bound by EIA conditions. Must integrate all corrective measures into the construction project and environmental monitoring plan.
  • Regional administration of Castilla y León: Involved in supervising compliance with sectoral conditions and protecting cultural heritage.
  • Duero River Basin Authority: Organism whose report has generated specific binding conditions for the project.
  • Municipalities and local entities in the Coscurita and Almazán area (Soria): Affected by work execution, although impacts are rated as compatible.
  • Wind farm promoters in the area: The new Coscurita substation is the evacuation infrastructure that enables connection of new renewable generation in Soria province.

Practical example

A wind farm promoter in the Almazán region with planned connection to the future Coscurita substation can now confirm that the evacuation infrastructure has approved environmental backing. The favorable conditional EIA means the 400 kV line can be built in an estimated 2-month period once work begins, allowing the wind farm promoter to adjust its own commissioning schedule.

However, if during execution of the 597 meters of line a breach of imposed conditions is detected—for example, in waste management or cultural heritage protection—the work can be halted by the environmental authority, delaying wind farm connection and generating significant additional costs for all parties involved.

Need to track this and other regulations?

Check the full details on CambiosLegales

What should companies do now?

  1. Red Eléctrica de España: Thoroughly review EIA conditions and integrate them into the final construction project before work begins. No condition is optional.
  2. Develop the environmental monitoring plan: The EIA requires monitoring during construction. Designate an environmental site manager with decision-making authority on the ground.
  3. Coordinate with the Duero River Basin Authority and the Junta de Castilla y León: Sectoral conditions from both organisms must be communicated to contractors and subcontractors before work begins.
  4. Wind farm promoters with planned connection in Coscurita: Update project schedules considering the estimated 2-month period for connection line construction.
  5. Waste management: Contract an authorized waste manager for the work phase and document all traceability, as this is one of the explicit corrective conditions of the EIA.

Frequently asked questions

What is the environmental impact assessment for the Almazán-Coscurita line and what does it authorize?

It is the resolution from the Directorate General for Quality and Environmental Assessment that gives environmental approval to the 400 kV overhead power line project promoted by Red Eléctrica de España. It authorizes construction of 597 meters of line with 3 steel lattice supports, but with mandatory corrective conditions on noise, emissions, waste and cultural heritage. Without this EIA, work cannot legally begin.

How long will construction of the 400 kV power line between Almazán and Coscurita take?

The estimated execution period is 2 months, according to data in the resolution published on October 28, 2026. This period is indicative and may be affected if breaches of EIA conditions are detected during work.

Why has this project been approved? What is its justification?

The project is justified for two reasons: it is part of the State's binding electrical planning and responds to the high wind potential of the Soria area, which requires new evacuation capacity to the 400 kV transport network. The new Coscurita substation is the key infrastructure for connecting future renewable generation in the region.

What organisms have imposed specific conditions in the EIA?

Two organisms have issued reports with specific conditions incorporated as obligations in the EIA: the Duero River Basin Authority and the Junta de Castilla y León. Their conditions are binding for Red Eléctrica de España during project execution.

Is there risk of impact on dwellings or inhabited areas?

No, according to the EIA. Impacts on atmosphere, noise and electromagnetic fields are rated as compatible because all inhabited areas are located more than 1 km from the line and no dwellings are detected in the 100-meter buffer around the route.

Official source

View complete regulation at official source

Notice: This article is purely informational in nature and does not constitute legal advice. For specific decisions, consult a qualified professional. Source: https://www.boe.es/diario_boe/txt.php?id=BOE-A-2026-22599



Share:
E
Equipo Editorial CambiosLegales

El equipo editorial de CambiosLegales analiza diariamente los cambios normativos que afectan a empresas y autónomos en España, ofreciendo análisis pro...

Comments

No comments yet. Be the first to comment!

Leave a comment
Activate alerts

Almost there